| Coordinates | 57°9′59.74″N 2°6′18.88″W / 57.1665944°N 2.1052444°W | 
| Construction started | May 2019 | 
| Completed | 2021 | 
| Opened | 2022 | 
| Cost | £35 million | 
| Owner | University of Aberdeen | 
The Science Teaching Hub is a building at the University of Aberdeen.
History
[edit]Plans for the building were revealed on 1 September 2017. Pending approval, teaching in the building was slated to begin in 2021 but the opening was delayed for a year due to the Covid pandemic.[1]
Planning permission was granted in August 2018.[2] Construction began in May 2019,[3] two months later than expected.[4] The building was completed in late 2021.[5]
Location
[edit]The building is situated within the university's Old Aberdeen campus on a site adjacent to the Sir Duncan Rice Library and the Fraser Noble Building.[1]
Design
[edit]The building was designed by Reiach and Hall Architects and is being built at a cost of £35 million.[2] The building will contain laboratories for students studying various subjects.[3]
References
[edit]- ^ a b "Plan for new £35m University of Aberdeen science building". BBC News. 1 September 2017. Retrieved 19 July 2021.
- ^ a b Morby, Aaron (28 August 2018). "£35m Aberdeen Uni science hub approved". Construction Enquirer News. Retrieved 19 July 2021.
- ^ a b "Robertson starts work on Aberdeen Uni's teaching hub". The Construction Index. 13 May 2019. Retrieved 19 July 2021.
- ^ Morrice, Emma (17 January 2019). "Work to begin on new Aberdeen science hub". Evening Express. Retrieved 19 July 2021.
- ^ "Robertson completes Science Teaching Hub for University of Aberdeen". Scottish Construction Now. 1 December 2021. Retrieved 26 January 2022.
 
	